THE STAGE 2 ROUTINE COMPLIANCE MONITORING PLAN, COMPLIANCE MONITORING PLAN SUMMARY SHEET AND MAP WERE APPROVED ON 6/21/16. APPROVAL WAS BASED UPON REVIEW OF THE SYSTEM¿S STAGE 1 MONITORING RESULTS FROM 2006-2012, 40/30 COMPLIANCE MONITORING PLAN, AND THE COMPLIANCE MONITORING PLAN SUMMARY SHEET. WE DID NOT RECEIVE DBP DATA FOR 2014 AND 2015.
BEGINNING IN 2016, STAGE 2 ROUTINE MONITORING WILL CONSIST OF 2 DUAL SAMPLE SETS (TTHM & HAA5), COLLECTED ANNUALLY, AT TWO LOCATIONS (01-A, 02-A), DURING THE MONTH OF SEPTEMBER.
THE NEXT SAMPLE IS DUE TO BE TAKEN IN SEPTEMBER 2016.
PLEASE BE SURE TO MARK THE CHAIN OF CUSTODY WITH THE SITE IDS AND STAGE 2 COMPLIANCE MONITORING SITE IDS TO ENSURE CORRECT SUBMISSION OF DWAR 32S FOR THESE SITES:
SITE ID STAGE 2 COMPLIANCE MONITORING SITE ID SAMPLE TYPE
01-A 2470 S KADOMOTO DR DUAL (TTHM & HAA5)
02-A 2677 S CANDLER DR DUAL (TTHM & HAA5)
|