THE ATTACHED STAGE 2 ROUTINE COMPLIANCE MONITORING PLAN, SUMMARY SHEET AND MAP WERE APPROVED 06/13/16. APPROVAL WAS BASED UPON REVIEW OF THE SYSTEM¿S STAGE 1 MONITORING RESULTS FROM 2006-2013, INITIAL DISTRIBUTION SYSTEM EVALUATION (IDSE) 40/30 CERTIFICATION (GRANTED ON 12/14/09) AND STAGE 1 REDUCED SAMPLING SCHEDULE (GRANTED ON 12/14/09). STAGE 2 SAMPLES COLLECTED (PRIOR TO THIS APPROVAL) DURING JULY 2014 AND SEPTEMBER 2015 MET THE REQUIREMENTS OF THE RULE AND WILL BE CREDITED TO THE SYSTEM.
IN 2014, STAGE 2 MONITORING WILL CONSIST OF DUAL SAMPLE SETS (TTHM & HAA5), COLLECTED ANNUALLY, AT ONE LOCATIONS (01-A), DURING THE MONTH OF SEPTEMBER.
IN 2015, STAGE 2 MONITORING WILL CONSIST OF DUAL SAMPLE SETS (TTHM & HAA5), COLLECTED ANNUALLY, AT ONE LOCATIONS (01-A), DURING THE MONTH OF JULY.
BEGINNING IN 2016, STAGE 2 MONITORING WILL CONSIST OF DUAL SAMPLE SETS (TTHM & HAA5), COLLECTED ANNUALLY, AT ONE LOCATIONS (01-A), DURING THE MONTH OF SEPTEMBER.
PLEASE BE SURE TO MARK THE CHAIN OF CUSTODY WITH THE SITE IDS AND STAGE 2 COMPLIANCE MONITORING SITE IDS TO ENSURE CORRECT SUBMISSION OF DWAR 32S FOR THESE SITES:
SITE ID STAGE 2 COMPLIANCE MONITORING SITE ID SAMPLE TYPE
01-A #2 END OF MONITOR ST. (6019 MONITOR ST.) DUAL (TTHM & HAA5)
|