THE STAGE 2 ROUTINE COMPLIANCE MONITORING SUMMARY SHEET (WITH EDITS FROM ORIGINAL SUBMITTAL) AND MAP (WITH EDITS FROM ORIGINAL SUBMITTAL) WAS APPROVED ON 07/22/16. APPROVAL WAS BASED UPON REVIEW OF THE SYSTEM¿S STAGE 1 MONITORING RESULTS FROM 2007-2013.
IN 2015, STAGE 2 MONITORING CONSISTED OF DUAL SAMPLE SETS (TTHM & HAA5), COLLECTED QUARTERLY, AT MULTIPLE LOCATIONS (01-A AND 02-A), DURING THE MONTHS OF FEBRUARY, APRIL, JULY, AND OCTOBER AT:
SITE ID STAGE 2 COMPLIANCE MONITORING SITE ID SAMPLE TYPE
01-A 20 SANDSTONE CT DUAL (TTHM & HAA5)
01-A 50 SANDSTONE CT DUAL (TTHM & HAA5)
01-A 30 SANDSTONE CT DUAL (TTHM & HAA5)
02-A 50 OASIS CT DUAL (TTHM & HAA5)
02-A 30 OASIS CT DUAL (TTHM & HAA5)
BEGINNING IN 3RD QUARTER 2016, STAGE 2 MONITORING WILL CONSIST OF DUAL SAMPLE SETS (TTHM & HAA5), COLLECTED QUARTERLY, AT TWO LOCATIONS (01-B AND 02-B), DURING THE MONTH OF JULY, (FOLLOWED BY OCTOBER, JANUARY, ETC.) AT:
SITE ID STAGE 2 COMPLIANCE MONITORING SITE ID SAMPLE TYPE
01-B 30 OASIS CT DUAL (TTHM & HAA5)
02-B 50 SANDSTONE CT DUAL (TTHM & HAA5)
|