THE STAGE 2 ROUTINE COMPLIANCE MONITORING PLAN (CMP), CMP SUMMARY SHEET AND MAP WERE APPROVED ON 06/10/16. APPROVAL WAS BASED UPON REVIEW OF THE SYSTEM¿S STAGE 1 MONITORING RESULTS FROM 2004-2013, STAGE 1 SAMPLING SCHEDULE, AND 40/30 CERTIFICATION (GRANTED 04/22/2009). STAGE 2 SAMPLES COLLECTED (PRIOR TO THIS APPROVAL) DURING AUGUST 2014 (WITH OCTOBER RESAMPLES OF HAA5S) AND AUGUST 2015 MET THE REQUIREMENTS OF THE RULE AND WILL BE CREDITED TO THE SYSTEM.
BEGINNING IN 2014, STAGE 2 MONITORING CONSISTS OF DUAL SAMPLE SETS (TTHM & HAA5), COLLECTED ANNUALLY, AT TWO LOCATIONS (01-A & 02-A), DURING THE MONTH OF AUGUST.
PLEASE BE SURE TO MARK THE CHAIN OF CUSTODY WITH THE SITE IDS AND STAGE 2 COMPLIANCE MONITORING SITE IDS TO ENSURE CORRECT SUBMISSION OF DWAR 32S FOR THESE SITES:
SITE ID STAGE 2 COMPLIANCE MONITORING SITE ID SAMPLE TYPE
01-A 407 MAIN STREET DUAL (TTHM & HAA5)
02-A 214 NICHOLS AVENUE DUAL (TTHM & HAA5)
|