THE ATTACHED STAGE 2 ROUTINE SUMMARY SHEET WAS APPROVED ON 7/5/16. APPROVAL WAS BASED UPON THE SYSTEM STARTING CHLORINATING ON APRIL 1, 2016.
BEGINNING IN 2016, STAGE 2 MONITORING WILL CONSIST OF AN INDIVIDUAL SAMPLE, COLLECTED ANNUALLY, AT TWO LOCATIONS (01-A & 02-A), DURING THE MONTH OF AUGUST. THIS APPROVAL REFLECTS THE AMENDED CMP FORM ON PAGE 2 AS DISCUSSED ON JULY 5, 2016.
PLEASE BE SURE TO MARK THE CHAIN OF CUSTODY WITH THE SITE IDS AND STAGE 2 COMPLIANCE MONITORING SITE IDS TO ENSURE CORRECT SUBMISSION OF DWAR 32S FOR EACH SITE:
SITE ID STAGE 2 COMPLIANCE MONITORING SITE ID SAMPLE TYPE
01-A 12079 NICOLE AVE INDIVIDUAL (TTHM)
02-A 14300 STANFORD INDIVIDUAL (HAA5)
|