THE DBP STAGE 2 ROUTINE COMPLIANCE MONITORING PLAN, COMPLIANCE MONITORING PLAN SUMMARY SHEET AND MAP WERE APPROVED ON 09/21/16. APPROVAL WAS BASED UPON REVIEW OF THE SYSTEM¿S COMPLIANCE MONITORING PLAN, SUMMARY SHEET, STAGE 1 DATA AND MAP.
BEGINNING IN OCTOBER 2013, STAGE 2 ROUTINE MONITORING WILL CONSIST OF 2 DUAL SAMPLE SETS (TTHM & HAA5), COLLECTED EVERY 90 DAYS(+/-2), 1ST MONTH OF EACH QUARTER (JANUARY, APRIL, JULY, OCTOBER), AT TWO LOCATIONS (01-A, 02-A)
PLEASE BE SURE TO MARK THE CHAIN OF CUSTODY WITH THE SITE IDS AND STAGE 2 COMPLIANCE MONITORING SITE IDS TO ENSURE CORRECT SUBMISSION OF DWAR 32S FOR THESE SITES:
SITE ID STAGE 2 COMPLIANCE MONITORING SITE ID SAMPLE TYPE
01-A 601 W ALLEN DUAL (TTHM & HAA5)
02-A 2042 MESA CR DUAL (TTHM & HAA5)
THE NEXT SAMPLE SHOULD BE TAKEN OCTOBER
|