THE STAGE 2 ROUTINE COMPLIANCE MONITORING PLAN SUMMARY SHEET, AND MAP WERE APPROVED ON 06/06/16. APPROVAL WAS BASED UPON REVIEW OF THE SYSTEM¿S STAGE 1 MONITORING RESULTS FROM 2004-2013, STANDARD MONITORING PLAN AND SUMMARY SHEET. STAGE 2 SAMPLES COLLECTED (PRIOR TO THIS APPROVAL) DURING NOVEMBER 2013 THROUGH FEBRUARY 2016 MET THE REQUIREMENTS OF THE RULE AND WILL BE CREDITED TO THE SYSTEM.
BEGINNING IN NOVEMBER 2013, STAGE 2 ROUTINE MONITORING WILL CONSIST OF DUAL SAMPLE SETS (TTHM & HAA5), COLLECTED EVERY 90 DAYS(+/-2), 3RD MONTH OF EACH QUARTER (FEBRUARY, MAY, AUGUST, NOVEMBER), AT FOUR LOCATIONS (01-A, 02-A, 03-A AND 04-A).
PLEASE BE SURE TO MARK THE CHAIN OF CUSTODY WITH THE SITE IDS AND STAGE 2 COMPLIANCE MONITORING SITE IDS TO ENSURE CORRECT SUBMISSION OF DWAR 32S FOR THESE SITES:
SITE ID STAGE 2 COMPLIANCE MONITORING SITE ID SAMPLE TYPE
01-A 6095 COUNTRY LANE W.W. DUAL (TTHM & HAA5)
02-A 2362 PINE LAKES DUAL (TTHM & HAA5)
03-A 5147 S.L. E. DUAL (TTHM & HAA5)
04-A 6695 WAGON WHEEL LANE DUAL (TTHM & HAA5)
|