THE STAGE 2 ROUTINE COMPLIANCE MONITORING PLAN, SUMMARY SHEET AND MAP WERE APPROVED ON 8/2/16. APPROVAL WAS BASED UPON REVIEW OF THE SYSTEM¿S STAGE 1 MONITORING RESULTS FROM 2004-2013, STAGE 2 INITIAL DISTRIBUTION SYSTEM EVALUATION (IDSE) VERY SMALL SYSTEM WAIVER (GRANTED 1/26/09) AND STAGE 1 SAMPLING SCHEDULE (GRANTED ON 8/11/09). STAGE 2 SAMPLES FOR 2014 AND 2015 WERE NOT COLLECTED AND WILL NOT BE CREDITED TO THE SYSTEM.
BEGINNING IN 2016, STAGE 2 MONITORING WILL CONSIST OF A DUAL SAMPLE SET (TTHM & HAA5), COLLECTED ANNUALLY, AT ONE LOCATION (01-A), DURING THE MONTH OF OCTOBER.
PLEASE BE SURE TO MARK THE CHAIN OF CUSTODY WITH THE SITE IDS AND STAGE 2 COMPLIANCE MONITORING SITE IDS TO ENSURE CORRECT SUBMISSION OF DWAR 32S FOR THESE SITES:
SITE ID STAGE 2 COMPLIANCE MONITORING SITE ID SAMPLE TYPE
01-A SP 117 DUAL (TTHM & HAA5)
|