THE STAGE 2 ROUTINE COMPLIANCE MONITORING PLAN SUMMARY SHEET AND MAP (WITH EDITS FROM ORIGINAL SUBMITTAL), WERE APPROVED ON 7/8/16. APPROVAL WAS BASED UPON REVIEW OF THE SYSTEM¿S STAGE 1 AND STAGE 2 MONITORING RESULTS FROM 2004-2015 AND THE IDSE STAGE 2 40/30 CERTIFICATION.
BEGINNING IN 2014, STAGE 2 MONITORING WILL CONSIST OF DUAL SAMPLE SETS (TTHM & HAA5), COLLECTED ANNUALLY, AT TWO LOCATIONS (01-A AND 02-A), DURING THE MONTH OF AUGUST, AT:
SITE ID STAGE 2 COMPLIANCE MONITORING SITE ID SAMPLE TYPE
01-A 3033 OAK CIRCLE ¿ LMS2DBP1 DUAL (TTHM & HAA5)
02-A 660 OAK AVE ¿ LMS2DBP2 DUAL (TTHM & HAA5)
BEGINNING IN 2016, STAGE 2 MONITORING WILL CONSIST OF DUAL SAMPLE SETS (TTHM & HAA5), COLLECTED ANNUALLY, AT TWO LOCATIONS (01-A AND 02-A), DURING THE MONTH OF JULY, AT:
SITE ID STAGE 2 COMPLIANCE MONITORING SITE ID SAMPLE TYPE
01-A 3033 OAK CIRCLE ¿ LMS2DBP1 DUAL (TTHM & HAA5)
02-A 660 OAK AVE ¿ LMS2DBP2 DUAL (TTHM & HAA5)
|