THE STAGE 2 ROUTINE COMPLIANCE MONITORING PLAN, INCREASED SUMMARY SHEET (PROVIDED) AND MAPS WERE APPROVED ON 05/31/16. APPROVAL WAS BASED UPON REVIEW OF THE SYSTEM¿S STAGE 1 MONITORING RESULTS FROM 2004-2013, AND THE INITIAL DISTRIBUTION SYSTEM EVALUATION (FINAL DRAFT JUNE 2010).
THE SYSTEM BEGAN STAGE 2 DBP ON ROUTINE MONITORING; HOWEVER, THE DURING THE FIRST MONITORING PERIOD OF STAGE 2 YOUR SYSTEM TRIGGERED TO INCREASED MONITORING.
BEGINNING IN 4TH QUARTER OF 2013, STAGE 2 MONITORING WILL CONSIST OF DUAL SAMPLES, COLLECTED EVERY 90 DAYS, AT TWO LOCATIONS (01-A AND 02-A) DURING THE FIRST WEEK OF THE SECOND MONTH OF EACH QUARTER (FEBRUARY, MAY, AUGUST (MONTH OF HIGHEST DBP CONCENTRATION), AND NOVEMBER).
PLEASE BE SURE TO MARK THE CHAIN OF CUSTODY WITH THE SITE ID AND STAGE 2 COMPLIANCE MONITORING SITE ID TO ENSURE CORRECT SUBMISSION OF DWAR 32 FOR EACH SITE:
SITE ID STAGE 2 COMPLIANCE MONITORING SITE ID SAMPLE TYPE
01-A BUILDING 153 DUAL (TTHM AND HAA5)
02-A BUILDING 1824 DUAL (TTHM AND HAA5)
|