THE STAGE 2 ROUTINE COMPLIANCE MONITORING PLAN, SUMMARY SHEET AND MAP WERE APPROVED ON 6/27/16. APPROVAL WAS BASED UPON REVIEW OF THE SYSTEM¿S STAGE 1 MONITORING RESULTS FROM 2004-2013. STAGE 2 STANDARD MONITORING PLAN, AND STAGE 1 SAMPLING SCHEDULE. NO STAGE 2 SAMPLES WERE COLLECTED FOR 2014 AND 2015 DUE TO THE SYSTEM BEING ON TRIANNUAL SAMPLING UNDER STAGE 1.
BEGINNING IN 2014, STAGE 2 MONITORING WILL CONSIST OF DUAL SAMPLES (TTHM & HAA5), COLLECTED ANNUALLY, AT ONE LOCATION (01-A), DURING THE MONTH OF SEPTEMBER.
SITE ID STAGE 2 COMPLIANCE MONITORING SITE ID SAMPLE TYPE
01-A EPDS001 DUAL
2015, STAGE 2 MONITORING WILL CONSIST OF DUAL SAMPLES, COLLECTED ANNUALLY, AT ONE LOCATION (01-A), DURING THE MONTH OF AUGUST.
SITE ID STAGE 2 COMPLIANCE MONITORING SITE ID SAMPLE TYPE
01-A STAND PIPE DUAL
BEGINNING IN 2016, STAGE 2 MONITORING WILL CONSIST OF INDIVIDUAL SAMPLES (TTHM & HAA5), COLLECTED ANNUALLY, AT TWO LOCATION (01-A), DURING THE MONTH OF AUGUST AND SEPTEMBER.
PLEASE BE SURE TO MARK THE CHAIN OF CUSTODY WITH THE SITE IDS AND STAGE 2 COMPLIANCE MONITORING SITE IDS TO ENSURE CORRECT SUBMISSION OF DWAR 32S FOR THESE SITES:
SITE ID STAGE 2 COMPLIANCE MONITORING SITE ID SAMPLE TYPE
01-A LAUNDRY ROOM TTHM INDIVIDUAL (AUGUST)
02-A MENS RESTROOM HAA5 INDIVIDUAL (SEPTEMBER)
|